Coastal GasLink stops work on section of pipeline route

Internal audit reveals clearing took place without valid archaeological impact assessments in place

Map of pipeline route showing location of Section 8 on which work has been stopped due to discrepancies with archaeological impact assessments. Coastal GasLink graphic.

Coastal GasLink (CGL) has stopped work on the last section of its pipeline project which runs from roughly south of Hazelton to Kitimat due to discrepencies with its archaelogical impact assessments.

In a statement on its website tonight, the company said it had discovered during an internal audit two areas where clearing has taken place in Section 8 contrary to its permits from the BC Oil and Gas Commission (OGC).

“At KP (kilometre post) 585, an area of approximately 600 metres long by 50 metres wide was cleared without an approved AIA in place,” the statement reads. “Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance. While clearing activities have taken place, minimal ground disturbance has occurred since the area has been used for transit and corduroy mats had been placed to limit disturbance.

READ MORE: NEB rejects federal review of Coastal GasLink pipeline

“At KP 631, due to a re-route, an area of approximately 240 metres by 10 metres was cleared without an AIA being completed. Areas adjacent to this location did have an approved AIA and were identified as low likelihood of archaeological significance”

CGL says it has voluntarily disclosed these incidents to (OGC), and the Environmental Assessment Office (EAO) and First Nations groups affected.

“Coastal GasLink is committed to protecting the environmental and cultural values of British Columbia during construction and operation of our natural gas pipeline,” said David Pfieffer, CGL president.

READ MORE: Gidimt’en launch civil lawsuit against Coastal GasLink

“Coastal GasLink regrets the errors that led to construction activities taking place without having approved archaeological impact assessments in place prior to start of construction.

“I have directed the team to complete a thorough investigation of these incidents and have halted clearing work in the area until the investigation is complete and recommendations are put into practice.

“I have also apologized to the impacted Indigenous communities and requested their participation in a proposed post-impact assessment.”



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

Drive-in movies such a success in Cowichan they doubled the features

One hundred per cent of the money collected is going to Nourish Cowichan.

Chemainus artist’s painting of a front-line worker a powerful image

Chemainus artist puts her creative touch to COVID Angel

Drivesmart column: Traffic calming in your neighbourhood

Since the police are only part of the solution, what are the alternatives?

B.C. accommodators need phone lines to light up as in-province travel given green light

Travel restrictions during the COVID-19 pandemic have decimated the tourism and hospitality industries

Man charged in Rideau Hall crash had rifle, shotguns, high-capacity magazine: RCMP

Hurren is accused of threatening to cause death or bodily harm to the prime minister

B.C. extends income assistance exemption for COVID-19

Provincial program to match Ottawa’s CERB, student pay

Indigenous B.C. tour operator keeps culture alive through virtual journeys in COVID-19 era

Campbell River based Homalco Tours is also setting up live cameras for bear viewing in Orford

Broadway veteran Nick Cordero dies from coronavirus complications

During Cordero’s hospitalization, Kloots sent him daily videos of her and their 1-year-old son, Elvis,

Northern communities welcome tourists as province opens to in-B.C. travellers

Officials have asked British Columbians to be careful as they travel this summer

300 Cache Creek residents on evacuation alert due to flood risk as river rises

Heavy rainfall on Canada Day has river rising steadily, threatening 175 properties

Most Read