The Trans Mountain expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C. (Canadian Press file images)

Trans Mountain pipeline expansion cost jumps 70% to $12.6 billion

The estimate of $7.4 billion was made in 2017 by the previous owner

The cost to build the Trans Mountain pipeline expansion has jumped by 70 per cent to $12.6 billion from a three-year-old estimate of $7.4 billion.

President and CEO Ian Anderson says the company owned by the federal government has spent $2.5 billion to date, including the impact of delays and additional regulatory processes, leaving an additional $8.4 billion needed to complete the project, plus $1.7 billion of financial carrying costs.

He says the project is now expected to be in service by December 2022.

The estimate of $7.4 billion was made in 2017 by the previous owner, Houston-based Kinder Morgan, Inc., which sold the expansion project and the existing pipeline to the federal government in 2018 for $4.5 billion.

Opponents have attacked the greenhouse gas emission and oil spill risks of the pipeline project but they’ve also charged it will be a money-loser with unproved markets in Asia that will fail financially and leave the public holding the bag.

ALSO READ: Opponents in B.C. to ramp up protests against Trans Mountain pipeline

Anderson says the company is recommending that Ottawa, as owner and lender, set aside a further $600 million reserve for cost impacts beyond the control of Trans Mountain.

Opponents of the pipeline expansion have vowed to do whatever it takes to stop the project despite losing a legal challenge before the Federal Court of Appeal earlier this week.

The four First Nations who lost the court challenge on Tuesday have 60 days to seek leave to appeal to the Supreme Court of Canada.

The expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Trans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Thanksgiving Food Drive coming to your door in Cowichan

Next week will be your chance to help meet the food crisis

Cowichan Community Centre Elder College celebrates 20th anniversary

Volunteer instructors are the key to success.

Flashback: Teddy bears, dinosaurs, cougars, oh my!

Remember these stories from Cowichan Lake?

Drivesmart column: Clear your frosty windows BEFORE driving

85 per cent of the information we require to drive safely comes to us through our eyes.

Unofficial holidays: Here’s what people are celebrating for the week of Sept. 20 to 26

Rabbit Day, Hobbit Day and One-Hit Wonder Day are all coming up this week

B.C. or Ontario? Residential school survivors fight move of court battle

It’s now up to Ontario’s Court of Appeal to sort out the venue question

B.C. transportation minister will not seek re-election

Claire Trevena has held the position since 2017

Body discovered floating in water near Lasqueti Island

JRCC reports personnel aboard fishing vessel made the find

Young B.C. cancer survivor rides 105-km with Terry Fox’s brother

Jacob Bredenhof and Darrell Fox’s cycling trek raises almost $90,000 for cancer research

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

B.C. migrant, undocumented workers rally for permanent residency program

Rally is part of the Amnesty for Undocumented Workers Campaign led by the Migrant Workers Centre

Preparations underway for pandemic election in Saskatchewan and maybe B.C.

Administrators in B.C. and around the country are also looking to expand voting by mail during the pandemic

Nearly 20 per cent of COVID-19 infections among health-care workers by late July

WHO acknowledged the possibility that COVID-19 might be spread in the air under certain conditions

Ferry riders say lower fares are what’s most needed to improve service

Provincial government announces findings of public engagement process

Most Read